Column Schedule from ETABS — Bars, Ties and Hoops for Every Column, Drawn and Exported to DXF

Reads every column's required steel from ETABS — live or from the Concrete Column Design Summary — groups the stories as you draw them on a long section, picks the bars and the IMRF or SMRF ties for rectangular, L and T columns, and draws the reinforcement schedule, ready to export to DXF or print as a rebar table.

ACI 318-08
Save calculationFree account — your numbers come with you.

1 · Columns from ETABS

Open the model, run Design ▸ Concrete Frame Design ▸ Start Design/Check, then run EtabsWebBridge.exe (Get EtabsWebBridge) and click Start Bridge. Every column comes in at every story with its section and the steel ETABS asks for, and the stories with their heights.

Loaded: Example: eight stories, seven columns

Same column, other labels

  • C8 at GF → C4 (same place)

2 · Frame and hoops

The code's limits still apply — the smaller governs, and the calculation names which. IMRF: 8 db, 24 dtie, half the least side and 12 in within ℓo; 16 db, 48 dtie, the least side and d/2 between.

3 · Bars

Sizes allowed (the smallest first)

Below plinth the cage runs on as laid above; the column is drawn the extra cover bigger all round — 2 in each way at 2.5 in over 1.5 in.

4 · Drawing

Long section — group the stories

5TH TO ROOF2 stories · cover 1½" · ℓo 2'-1"4-Ø20 + 6-Ø16 Ø10 @ 4" / 6"3RD TO 5TH2 stories · cover 1½" · ℓo 2'-1"4-Ø20 + 6-Ø16 Ø10 @ 4" / 6"1ST TO 3RD2 stories · cover 1½" · ℓo 2'-1"10-Ø28 + 2-Ø25 Ø10 @ 4" / 6"GF TO 1ST1 story · cover 1½" · ℓo 2'-6"8-Ø28 + 6-Ø25 Ø10 @ 4" / 6"FDN TO GF1 story · cover 2½", 2" bigger · ℓo 2'-11"14-Ø28 Ø10 @ 4" full heightROOFEL 76.00'10'-0"6THEL 66.00'10'-0"5THEL 56.00'10'-0"4THEL 46.00'10'-0"3RDEL 36.00'10'-0"2NDEL 26.00'10'-0"1STEL 16.00'10'-0"GFEL 6.00'6'-0"FDNC 15X25C 15X25C 15X25C 15X25C 15X25C 15X25C 15X30C 15X35Split the group at 6TH+Join the groups at 5TH−Split the group at 4TH+Join the groups at 3RD−Split the group at 2ND+Join the groups at 1ST−Join the groups at GF−

Click + at a level to start a new group there, − to join the two groups it divides. Name a group as the drawing should head it (e.g. BELOW PL, GROUND FLOOR); left blank it takes its levels. Bars typed for a cell stay with their stories when you regroup.

Story heights

Columns reinforcement schedule

100 %
COLUMNS REINFORCEMENT SCHEDULEConcrete cylinder strength, f'c = 4,000 psi min.Suggested mix ratio (1 : 1¼ : 2½)Designationof columnFDN TO GFGF TO 1ST1ST TO 3RD3RD TO 5TH5TH TO ROOFC1, C3(2 Nos)5.19" c/c7.58" c/c22"14"8-Ø162½" clear coveraround tiesℓo = 1'-8" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c5.19" c/c7.58" c/c20"12"8-Ø161½" clear coveraround tiesℓo = 1'-8" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c5.19" c/c7.58" c/c20"12"8-Ø161½" clear coveraround tiesℓo = 1'-8" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c5.19" c/c7.58" c/c20"12"8-Ø161½" clear coveraround tiesℓo = 1'-8" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c5.19" c/c7.58" c/c20"12"8-Ø161½" clear coveraround tiesℓo = 1'-8" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/cC2(1 No)5.15" c/c6.58" c/c27"13"10-Ø162½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4" c/c5.15" c/c6.58" c/c25"11"10-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4" c/c5.15" c/c6.58" c/c25"11"10-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4" c/c5.15" c/c6.58" c/c25"11"10-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4" c/c5.15" c/c6.58" c/c25"11"10-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4" c/cC4(1 No)5.09" c/c5.21" c/c32"17"4-Ø20+10-Ø162½" clear coveraround tiesTie set A: Ø10 @ 4" c/c- Ø20- Ø165.09" c/c5.21" c/c30"15"4-Ø20+10-Ø161½" clear coveraround tiesℓo = 2'-6" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø166.81" c/c5.21" c/c25"15"4-Ø20+6-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø166.81" c/c5.21" c/c25"15"4-Ø20+6-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø166.81" c/c5.21" c/c25"15"4-Ø20+6-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø16C5(1 No)4.35" c/c7.43" c/c37"14"16-Ø202½" clear coveraround tiesTie set A: Ø10 @ 4" c/c4.35" c/c7.43" c/c35"12"16-Ø201½" clear coveraround tiesℓo = 2'-11" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c4.35" c/c7.43" c/c35"12"16-Ø201½" clear coveraround tiesℓo = 2'-11" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c4.35" c/c7.43" c/c35"12"12-Ø20+4-Ø161½" clear coveraround tiesℓo = 2'-11" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c- Ø20- Ø165.07" c/c7.43" c/c35"12"12-Ø20+2-Ø161½" clear coveraround tiesℓo = 2'-11" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 4½" c/c- Ø20- Ø16C6(1 No)6.02" c/c5.06" c/c37"17"14-Ø282½" clear coveraround tiesTie set A: Ø10 @ 4" c/c5.02" c/c5.06" c/c30"15"8-Ø28+6-Ø251½" clear coveraround tiesℓo = 2'-6" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø28- Ø255.03" c/c5.06" c/c25"15"10-Ø28+2-Ø251½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø28- Ø256.81" c/c5.21" c/c25"15"4-Ø20+6-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø166.81" c/c5.21" c/c25"15"4-Ø20+6-Ø161½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø16C7(1 No)26"26"6-Ø20+10-Ø162½" clear coveraround tiesBars @ 4.67"–5.43" c/cℓo = 2'-0" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø1610"10"24"24"6-Ø20+10-Ø161½" clear coveraround tiesBars @ 4.67"–5.43" c/cℓo = 2'-0" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø20- Ø1610"10"24"24"16-Ø161½" clear coveraround tiesBars @ 4.67"–5.58" c/cℓo = 2'-0" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c10"10"24"24"16-Ø161½" clear coveraround tiesBars @ 4.67"–5.58" c/cℓo = 2'-0" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c10"10"24"24"16-Ø161½" clear coveraround tiesBars @ 4.67"–5.58" c/cℓo = 2'-0" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/cOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculationOpen this cell's bars and calculation

6 types from 7 columns; click a cell to open it. The DXF draws every section at full size (inches): each tie one polyline with its hooks, larger bars filled, smaller as rings.

Column plan

ABC123C1C2C3C4C5C6C7COLUMN LAYOUT PLAN — FDN TO GFC1C2C3 (ETABS C5)C4 (ETABS C3)C5 (ETABS C4)C6C7

Each column at its place in FDN TO GF, turned as in ETABS and marked as the schedule marks it (C1, C2… from the top row, left to right, then down); click one to open it. The DXF is in global coordinates, inches.

Versions — keep and compare

Keep a version when you issue the schedule (Rev 0), then again after the model changes: this card shows which columns' bars, ties or sections changed, story by story. Versions stay in this browser; download one as a file to keep it elsewhere or send it.

C6 · 1ST TO 3RD

ETABS C6
5.03" c/c5.06" c/c25"15"10-Ø28+2-Ø251½" clear coveraround tiesℓo = 2'-1" min.Tie set A: Ø10 @ 4" c/cTie set B: Ø10 @ 6" c/c- Ø28- Ø25
Section
C 15X25 — 25 × 15 in
As required
11.00 in² at 2ND
As provided
11.07 in² 0.994
Bar spacing
3x5 per face (short × long): 5.03" c/c along 25 in, 5.06" along 15 in
Tie legs
2/3 (long / short): 2 along the 25 in side, 3 along the 15 in side
Hoops
Ø10 @ 4" within ℓo 25" (by your 4 in limit), @ 6" between (by your 6 in limit)

Bars per face as ETABS writes them: 3x6 is 3 bars along each 15 in face and 6 along each 25 in face, corners counted on both (14 bars). Tie legs 2/4: 2 legs running along the 25 in side, 4 along the 15 in side — never fewer than the code's tie rules need. Bundles (ACI 318-08 §7.6.6): 2 to 4 bars in contact at a position, the corners first; each bundle counts as one position, so the spacing opens up, and its clear spacing is checked as the single bar of the same area. Tie set A (within ℓo) and B (the middle zone): blank keeps the designed spacing; a spacing over the code's limit is kept and flagged. Leave the bars as designed to have them chosen for the layout and bundles.

Match properties — the rebar arrangement, not the size

Every column, every group

ETABSMarkFDN TO GFGF TO 1ST1ST TO 3RD3RD TO 5TH5TH TO ROOF
C1C1
C2C2
C5C3
C3C4
C4C5
C6C6
C7C7

required/provided under 0.750.75–1.00over 1.00 or none fits✎ typed by hand

Design checks

CheckDemandCapacityDCRStatus
Steel provided against steel required11.00 in²11.07 in²0.994✓ OK
Clear spacing along the 25 in face1.65 in3.93 in0.421✓ OK
Clear spacing along the 15 in face1.65 in3.95 in0.418✓ OK
Steel ratio at most 0.080.02950.080.369✓ OK
Steel ratio at least 0.010.010.02950.339✓ OK
Tie set A spacing4.0 in7.50 in0.533✓ OK
Tie set B spacing6.0 in6.28 in0.956✓ OK

Calculation

  1. 1Steel required
    A_{s,req} = \max_{\text{stories}} A_s
    A_{s,req} = 11.00 \ \text{at 2ND}
    A_{s,req}11.00 in²

    ETABS's As over 3RD, 2ND; its minimum there 3.75 in².

  2. 2Bars chosen
    A_{s} = \textstyle\sum n \, \pi d_b^2 / 4
    A_s = 10 imes 0.954 + 2 imes 0.761 = 11.07
    A_s11.07 in²

    10-Ø28 + 2-Ø25: 5 bars along each 25 in face and 3 along each 15 in face, corners included (3x5 short × long); Ø28 at the corners and the bars nearest them.

  3. 3Required/provided against your max
    \text{DCR} = A_{s,req} / A_s \le \text{your max}
    \text{DCR} = 11.00 / 11.07 = 0.994 \ (\text{max } 1.00)
    \text{DCR}0.994

    Within your max of 1.00: the bars give at least As required ÷ 1.00.

  4. 4Bar spacing along the 25 in face
    s = \dfrac{L - 2(c_c + d_t) - d_b}{n - 1}
    s = \dfrac{25.0 - 2(1.50 + 0.394) - 1.102}{5 - 1} = 5.03
    s_{B}5.03 in

    Centre to centre; your limits 4.0–8.0 in.

  5. 5Bar spacing along the 15 in face
    s = \dfrac{L - 2(c_c + d_t) - d_b}{n - 1}
    s = \dfrac{15.0 - 2(1.50 + 0.394) - 1.102}{3 - 1} = 5.06
    s_{H}5.06 in

    Centre to centre; your limits 4.0–8.0 in.

  6. 6Steel ratio
    \rho_g = A_s / A_g
    \rho_g = 11.07 / (25.0 \times 15.0) = 0.0295
    \rho_g0.0295
  7. 7Length ℓo at each endACI 318-08, document reference
    \ell_o \ge \max(\ell_n / 6,\ c_{max},\ 18\text{ in})
    \ell_o = \max(102.0 / 6,\ 25.0,\ 18) \to 25
    \ell_o25 in

    ℓn = 102.0 in, the tallest story of the group (120.0 in) less the beam; rounded up to the inch.

  8. 8Tie set A (within ℓo)ACI 318-08, document reference
    s_A \le \min(8 d_b,\ 24 d_t,\ c_{min}/2,\ 12\text{ in},\ \text{your cap})
    s_A = 4.0 \ (\text{your 4 in limit})
    s_A4.0 in

    Ø10 hoops, 2/3 legs (long / short): 2 running along the 25 in side and 3 along the 15 in side; the code limit 7.50 in, rounded down to 0.50 in.

  9. 9Tie set B (middle zone)ACI 318-08, document reference
    s_B \le \min(16 d_b,\ 48 d_t,\ c_{min},\ d/2,\ \text{your cap})
    s_B = 6.0 \ (\text{your 6 in limit})
    s_B6.0 in

    The code limit 6.28 in: d/2 for shear, d = 12.56 in across the 15 in side.

Notes

  • Sheet for C6, 1ST TO 3RD (C 15X25, 25 × 15 in) — the cell with the highest required to provided.

Assumptions

  • The steel each column needs at each story is ETABS's concrete frame design As (the larger of the P-M demand and the minimum); a group of stories takes the largest of its stories.
  • Bars: 16 mm first; the next size up mixed in at the corners, then at the face bars nearest the corners (the bars farthest from both axes add most to the column's strength), before that size is used throughout. A larger size is taken only when the smaller can't give the steel, or when it saves more than 5 % of it. Of the layouts that fit, the least steel wins, giving at least the steel required ÷ your max required/provided of 1.00.
  • Bars 4.0 in to 8.0 in apart centre to centre along each face, and at least the code's clear spacing; each bar's centre the clear cover, the tie and half the bar in from the face.
  • Ties: every corner and alternate bar held by a tie corner, none more than 6 in clear from a held bar; two neighbouring held bars share a closed inner tie, a lone one takes a crosstie. Every tie a closed hoop with 135° hooks.
  • Going down a column, a group keeps at least the bars of the group above — as many, each as large; where the column gets bigger below, fewer bars are allowed there, with as much steel and the largest bar no smaller.
  • IMRF: hoops at tie set A within ℓo at each end and tie set B between; ℓn is the tallest story of the group less a 18 in beam. Your caps: 4.0 in within ℓo, 6.0 in in the middle zone.
  • Below plinth (FDN TO GF): 2.5 in clear cover, the column drawn 2.0 in bigger each way than its ETABS section. The bars and ties are designed on ETABS's section with the 1.5 in cover above — the extra cover carries nothing (ACI 318-08 §10.8.4) — so the cage runs on unchanged.

What this calculator does not check

  • No interaction diagram is drawn: the bars carry the steel area ETABS's design asks for, placed by the rules above. Re-check in ETABS with the bars as provided if the arrangement departs much from ETABS's own.
  • Lap splices, their location and their ties, and the joint (beam-column) reinforcement are not designed.
  • The tie clause numbers are the edition's (ACI 318-08) as a whole until confirmed (OPEN-QUESTIONS §19).
  • Rectangular columns only.

Results are for preliminary sizing and educational use. They are not a design and must be reviewed, verified and sealed by a licensed or registered engineer before being used in construction.

column-schedule v1.8.1 · ACI 318-08 · input 6e72f23f1c14c491