RC Beam Detailing from ETABS — Bars, Cutoffs and SMRF/IMRF Hoops, Drawn and Checked to ACI 318

Reads a continuous beam's design straight from ETABS through the bridge — every span's required steel, the columns at its supports, Vg and Pu — and details it: continuous and extra bars with their cutoffs, SMRF or IMRF hoops, the capacity-design shear and the full compliance checklist, drawn as a long section with sections, ready for DXF.

ACI 318-08ACI 318-19
Save calculationFree account — your numbers come with you.

1 · Beam from ETABS

  1. In ETABS, run the analysis and Design ▸ Concrete Frame Design ▸ Start Design/Check.
  2. Select the beam's frame objects — every span of the line (selecting the columns too does no harm).
  3. Run the EtabsWebBridge 1.3.0 or later — the program, or the ETABS plugin from Tools ▸ Add/Show Plug-Ins (Get EtabsWebBridge) — and click Start Bridge, then the button above.

The spans, their sizes, f'c and fy, the steel ETABS asks for at every station, the columns at each support (for the clear span), Vg and Pu all come in (1.3.2 also sends the moments, shears and torsions), and stay editable.

Loaded: Example: FB-05C, two spans

2 · Frame and materials

Each zone starts from the least set: within 2h of an SMF's face every corner and alternate bar is held (none more than 6 in clear from a held one, §21.5.3.3), and a crosstie is added where the demand or Ve would close the hoops below 4 in (torsion counts on the two outer legs only).

Main bar sizes the detailer may use

Top and bottom bars, continuous and extra. Bars you type are kept whatever their size.

As PCA Notes' Example 29.2: where φMn of the continuing bars meets Mu, + max(d, 12db) (§12.10.3); ≥ ℓd past the face (§12.10.4); the farthest third of the top steel past the inflection point (§12.12.3); §12.10.5 at the cut. In an SMF the diagram includes the probable moments at the faces with gravity.

Where ETABS reads a torque at a station, the transverse and longitudinal torsion steel is the larger of ETABS's and the code's from that torque (§11.5, the shear-torsion calculator's equations, θ = 45°, λ = 1). The checklist names the code's rows.

By CRSI's table of the most bars in one layer. In a 12" web: 4 × Ø16, 4 × Ø20, 3 × Ø25, 3 × Ø28, 3 × Ø32. The size that takes the fewest layers is chosen first.

Extra bars fill the continuous bars' layer first, then the next — never one bar alone in a second layer: one comes down from the first.

Where the top bars' hooks don't fit the end column, the face holds only what they develop (φMn); the rest of the moment goes to mid-span (+½ΔM), and the bottom bars are sized again for it (§8.4).

3 · Spans and supports

B5 · 16'-0" c/c
B6 · 16'-2" c/c
SupportColumnc1, inc2, in
A
B
C

0 for no column (a cantilever's tip) or one not known — its checks then say so.

Detailed — all checks passLargest required/provided 0.99Checklist: 39 pass, 0 fail, 6 to confirmTop 3-Ø16, bottom 3-Ø20, 4 extra bar sets

Reinforcement detail

Sections
fit
BEAM FB-05C — LONG SECTION12" × 24" · special moment frame (SMF) · f'c 4,000 psi · fy 60,000 psi · clear cover 1.5" · hoops Ø10, legs by zone · ACI 318-08AC1BC2CC316'-0" c/cℓn = 14'-6"16'-2" c/cℓn = 14'-8"T1 3-Ø16 continuousB1 3-Ø20 continuousT2 1-Ø20 + 4-Ø167'-3"T3 1-Ø207'-0"7'-0"T4 2-Ø205'-9"5'-9"T5 1-Ø204'-6"2h = 4'-0"2-leg Ø10 @ 3" (1st at 2")6'-6"2-leg Ø10 @ 7"2h = 4'-0"2-leg Ø10 @ 3" (1st at 2")2h = 4'-0"2-leg Ø10 @ 3" (1st at 2")6'-8"2-leg Ø10 @ 7"2h = 4'-0"2-leg Ø10 @ 3" (1st at 2")Top D/CBottom D/C0.990.68at A0.930.96mid A–B0.970.67at B0.930.84mid B–C0.930.59at CSECTIONS — none cut yet: choose where on the long sectionBAR SCHEDULEMarkBarsWhereLengthRuleT13-Ø16top, continuous34'-7"at least 2 continuous (§21.5.2.1); 90° hooks into the end columns, ℓdh 0'-9"B13-Ø20bottom, continuous34'-11"M+ ≥ ½ M− at each face (§21.5.2.2)T21-Ø20 + 4-Ø16top, at A9'-5"7'-3" past the face — moment diagram + d or 12db (§12.10.3); ℓd 3'-1"T31-Ø20top, at B15'-6"7'-0" past the face — moment diagram + d or 12db (§12.10.3); ℓd 3'-1"T42-Ø20top, at B, layer 213'-0"5'-9" past the face — moment diagram + d or 12db (§12.10.3); ℓd 3'-1"T51-Ø20top, at C6'-8"4'-6" past the face — moment diagram + d or 12db (§12.10.3); ℓd 3'-1"S16-Ø10sides, 3 each face, continuous33'-4"(2/3)·Al of torsion, half on each face (§11.6.6)H1Ø10 hoops, 2 legsspan A–B: 43; span B–C: 435'-6" eachclosed, 135° hooks; 2h zones at each face, first 2" from the face (§21.5.3)Open this span's calculationOpen this span's calculationChange T1Change B1Change T2Change T3Change T4Change T5Change confined hoops of span 1Change middle hoops of span 1Change confined hoops of span 2Change middle hoops of span 2Change T1Change B1Change T2Change T3Change T4Change T5Change S1

Continuous bars blue, extra bars red with their marks and lengths past each column face, hoops purple, side bars green. Click any bar, its label, its row in the schedule or a hoop zone to change it. Dimensions and text are sized for 1:50. The DXF is the long section only, on its own layers (BEAM-REBAR-CONT, BEAM-REBAR-EXTRA, BEAM-HOOPS…), in inches.

ETABS data along the beam

Steel ETABS designed, at each station

Flexural steeltop 2.05, bottom 1.20 in² at most
Top AsBottom As
0.001.002.00ABC2.051.20
Torsional steelAl 0.90 in², At/s 0.12 in²/ft at most
Al (in²)
0.000.250.500.75ABC0.90
At/s (in²/ft)
0.000.050.10ABC0.12
Shear steelAv/s + 2At/s 0.60 in²/ft at most
Av/sAv/s + 2At/s
0.000.200.400.60ABC0.360.60

Forces against what the bars provide (ETABS's signs; tick to lay the capacity over the demand)

Moment (from the steel ETABS asked for)φMn ≥ Mu all along
Mu+ (ETABS's As)Mu− (ETABS's As)φMn+ (bottom bars)φMn− (top bars)
-2000.00ABC112-186136-237

φMn = 0.9·As·fy·(d − a/2) of the continuous bars and every extra bar over the point, each taken as developed along its length.

Shear (capacity-design Ve)φVn ≥ Ve all along
+Ve−Ve+φVn−φVn
-50.00.0050.0ABC53.0-53.079.3-79.3

φVn = 0.75·(Vc + Av·fyt·d/s) with each zone's legs and spacing; Vc = 0 within 2h of an SMF's face (§21.5.4.2); Vs ≤ 8√f'c·bw·d.

Torsion (from the At/s ETABS asked for)φTn ≥ Tu all along
+Tu (ETABS's At/s)−Tu (ETABS's At/s)+φTn−φTn
-50.00.0050.0ABC11.3-11.345.9-45.9

φTn = 0.75·2·Ao·At·fyt/s (θ = 45°, Ao = 0.85·Aoh, At one outer leg; §11.5.3.6), each zone's spacing. The hoops carry shear and torsion together: their check is Av/s + 2At/s, in the hoop zones.

Cut-off lengths of the extra bars

How far each extra bar runs, worked out4 extra bar sets
T21-Ø20 + 4-Ø16 top, at A7'-3" (87") past each face · bar 9'-5"
  1. Bars that continue past the cut: 0.93 in² → φMn = 88.5 kip·ft
  2. From the A face into span A–B: Mu = φMn of the continuing bars at 64.5" (Mpr + gravity)
  3. + max(d, 12db) = max(21.7, 9.4) = 21.7" → 86.2" (§12.10.3)
  4. ℓd past the face = 37.3" (SMF §21.7.5 (3.25·ldh)) (§12.10.4)
  5. Largest 86.2" → rounded up to 3": 87"
  6. At the cut in span A–B: Vu 35.0 ≤ ⅔φVn 39.1 kip ✓
T31-Ø20 top, at B7'-0" (84") past each face · bar 15'-6"
  1. Bars that continue past the cut: 0.93 in² → φMn = 88.5 kip·ft
  2. From the B face into span B–C: Mu = φMn of the continuing bars at 59.4" (Mpr + gravity)
  3. From the B face into span A–B: Mu = φMn of the continuing bars at 58.7" (Mpr + gravity)
  4. + max(d, 12db) = max(21.7, 9.4) = 21.7" → 81.1" (§12.10.3)
  5. ℓd past the face = 37.3" (SMF §21.7.5 (3.25·ldh)) (§12.10.4)
  6. Largest 81.1" → rounded up to 3": 84"
  7. At the cut in span B–C: Vu 33.4 ≤ ⅔φVn 39.1 kip ✓
  8. At the cut in span A–B: Vu 34.4 ≤ ⅔φVn 39.1 kip ✓
T42-Ø20 top, at B, layer 25'-9" (69") past each face · bar 13'-0"
  1. Bars that continue past the cut: 1.42 in² → φMn = 132.2 kip·ft
  2. From the B face into span B–C: Mu = φMn of the continuing bars at 45.5" (Mpr + gravity)
  3. From the B face into span A–B: Mu = φMn of the continuing bars at 44.9" (Mpr + gravity)
  4. + max(d, 12db) = max(21.7, 9.4) = 21.7" → 67.2" (§12.10.3)
  5. ℓd past the face = 37.3" (SMF §21.7.5 (3.25·ldh)) (§12.10.4)
  6. Largest 67.2" → rounded up to 3": 69"
  7. At the cut in span B–C: Vu 36.5 ≤ ⅔φVn 39.1 kip ✓
  8. At the cut in span A–B: Vu 36.7 ≤ ⅔φVn 39.1 kip ✓
T51-Ø20 top, at C4'-6" (54") past each face · bar 6'-8"
  1. Bars that continue past the cut: 0.93 in² → φMn = 88.5 kip·ft
  2. From the C face into span B–C: Mu = φMn of the continuing bars at 32.3" (ETABS's As)
  3. + max(d, 12db) = max(21.7, 9.4) = 21.7" → 54.0" (§12.10.3)
  4. ℓd past the face = 37.3" (SMF §21.7.5 (3.25·ldh)) (§12.10.4)
  5. Largest 54.0" → rounded up to 3": 54"
  6. At the cut in span B–C: Vu 32.0 ≤ ⅔φVn 39.1 kip ✓

d = 21.7, 21.7" by span. The moment diagram is the envelope of ETABS's M3 (or the moment of the steel ETABS asked for) and the probable moments at the faces with the gravity load, sway either way (w = 2Vg/ℓn, ¾ of it for the negative moments). The bar length adds the column between two runs, and hooks where a bar ends in an end column.

Estimate

Bill of materials and coststeel 317 kg, concrete 1.65 m³
MarkWhereBarNo.EachTotal, mWeight, kg
T1top, continuousØ16334'-7" (10.55 m)31.6550.0
B1bottom, continuousØ20334'-11" (10.65 m)31.9478.8
T2top, at AØ2019'-5" (2.87 m)2.877.1
T2top, at AØ1649'-5" (2.87 m)11.4818.1
T3top, at BØ20115'-6" (4.72 m)4.7211.7
T4top, at B, layer 2Ø20213'-0" (3.96 m)7.9219.5
T5top, at CØ2016'-8" (2.03 m)2.035.0
S1sides, 3 each face, continuousØ10633'-4" (10.17 m)60.9937.6
H1span A–B, hoopsØ10435'-6" (1.68 m)72.0944.4
H1span B–C, hoopsØ10435'-6" (1.68 m)72.0944.4
By sizeLength, mkg/mWeight, kg
Ø10205.160.617126.5
Ø1643.121.57868.1
Ø2049.482.466122.0
Steel316.6
Concrete: 1.65 m³ (58.33 cft)
Formwork: 13.55 m² (145.8 sft)
Steel: 191.7 kg/m³ of concrete
Rates
ItemQuantityRateAmount
Reinforcing steel (+5% laps and wastage)332.41 kg——
Concrete1.65 m³——
Formwork (soffit and sides)13.55 m²——
Totalenter the rates
Bars as scheduled, hooks included; hoops and crossties as drawn; concrete and forms over the clear spans. Laps aren't laid out: the allowance covers them. Steel at 7,850 kg/m³ (d²/162.2 kg/m).

Bars — type any to change them

MarkWhereRequired, in²Bars, in²Type to changeLength past the faceGoverns
T1top, continuous0.873-Ø16 0.93hooked at the endsleast top requirement, continuity
B1bottom, continuous1.403-Ø20 1.46hooked at the endslargest mid-span requirement, As,min
S1sides (torsion)0.606-Ø10 0.73continuous(2/3)·Al = 0.60 in²
T2top extra, at A1.722.65 − 0.93 (T1)1-Ø20 + 4-Ø16 1.737'-3"moment diagram + d or 12db (§12.10.3); ℓd 3'-1"
T3top extra, at B1.402.33 − 0.93 (T1)1-Ø20 0.497'-0"moment diagram + d or 12db (§12.10.3); ℓd 3'-1"
T4top extra, at B, layer 2with layer 12-Ø20 0.975'-9"moment diagram + d or 12db (§12.10.3); ℓd 3'-1"
T5top extra, at C0.381.32 − 0.93 (T1)1-Ø20 0.494'-6"moment diagram + d or 12db (§12.10.3); ℓd 3'-1"

Bars as 2-d20+1-d16 (or 2-Ø20 + 1-Ø16). A bar typed by hand is kept and its D/C shown — nothing is enlarged behind your back. Blank goes back to the designed bars.

Hoops

SpanZoneLegsSet legsØ10 @Set your own, inGovernsVes from Ve
A–B2h = 4'-0" each end2 a closed hoop3"§21.5.353.0 kip4.5"
A–Bbetween2 a closed hoop7"torsion (§11.6.6.1)
B–C2h = 4'-0" each end2 a closed hoop3"§21.5.350.6 kip4.7"
B–Cbetween2 a closed hoop7"torsion (§11.6.6.1)

Required and provided along the beam

in²at Amid A–Bat Bmid B–Cat C
ETABS top2.050.301.800.290.95
Al (torsion)0.900.300.800.200.55
Top required2.650.872.330.871.32
Top provided2.670.932.400.931.42
Top D/C0.990.930.970.930.93
ETABS bottom0.401.200.451.100.50
Bottom required1.001.400.981.230.87
Bottom provided1.461.461.461.461.46
Bottom D/C0.680.960.670.840.59
Set byETABStop: As,min (§10.5.1)ETABStop: As,min (§10.5.1)bottom: As,min (§10.5.1)

Required = ETABS + (2/3)·Al, at least As,min and the seismic moment ratios. A support takes the outer tenth of each span, mid-span the middle third.

SMRF checklist — ACI 318-08

1. Section limits

  • PASSspan 1: clear span ln ≥ 4d 08 §21.5.1(b)
    ln/d = 174.0/21.71 = 8.0 (≥ 4)
  • PASSspan 1: width ≥ min(0.3h, 10 in) 08 §21.5.1(c)
    b = 12.0 in, 0.3h = 7.2 in, at least 10 in
  • N/Aspan 1: Pu ≤ Ag·f'c/10 08 §21.5.1(a)
    axial not read from the model; the limit is 115.2 kip — read the beam from ETABS (the analysis must have been run) or type Pu
  • PASSspan 1: width vs supporting column 08 §21.5.1(d)
    b = 12.0 in ≤ c2 + 2·min(c2, 0.75c1) = 45.0 in at support 1
  • PASSspan 2: clear span ln ≥ 4d 08 §21.5.1(b)
    ln/d = 176.0/21.71 = 8.1 (≥ 4)
  • PASSspan 2: width ≥ min(0.3h, 10 in) 08 §21.5.1(c)
    b = 12.0 in, 0.3h = 7.2 in, at least 10 in
  • N/Aspan 2: Pu ≤ Ag·f'c/10 08 §21.5.1(a)
    axial not read from the model; the limit is 115.2 kip — read the beam from ETABS (the analysis must have been run) or type Pu
  • PASSspan 2: width vs supporting column 08 §21.5.1(d)
    b = 12.0 in ≤ c2 + 2·min(c2, 0.75c1) = 45.0 in at support 2

2. Longitudinal reinforcement

  • PASSat least 2 continuous bars top and bottom 08 §21.5.2.1
    top 3-d16, bottom 3-d20
  • PASSAs ≥ As,min on both faces at every section 08 §21.5.2.1
    worst top at mid1: 0.935 vs As,min 0.869 in²
  • PASSreinforcement ratio ρ ≤ 0.025 08 §21.5.2.1
    max ρ = 0.0102 at support1
  • PASSflexural D/C ≤ 1.05 (all locations) 08 §9.3
    max D/C = 0.99
  • PASSsupport 1: Mn+ ≥ 50% Mn− at the face 08 §21.5.2.2
    Mn+ 150.7 vs 0.50·Mn− 131.8 kip·ft
  • PASSsupport 2: Mn+ ≥ 50% Mn− at the face 08 §21.5.2.2
    Mn+ 150.7 vs 0.50·Mn− 119.5 kip·ft
  • PASSsupport 3: Mn+ ≥ 50% Mn− at the face 08 §21.5.2.2
    Mn+ 150.7 vs 0.50·Mn− 73.5 kip·ft
  • PASSany section Mn ≥ 25% of the largest at the faces 08 §21.5.2.2
    least Mn 98.3 vs 0.25·263.5 = 65.9 kip·ft (at mid1)

3. Transverse reinforcement

  • PASSspan 1: hoop zone = 2h from each face 08 §21.5.3.1
    ℓo = 48.0 in (2h = 48.0 in)
  • PASSspan 1: first hoop ≤ 2 in from the face 08 §21.5.3.2
    first hoop at 2.0 in
  • PASSspan 1: hoop spacing within ℓo 08 §21.5.3.2
    s = 3 in ≤ 3.8 in (6db governs of d/4 = 5.4, 6db = 3.8, 6 in = 6.0; smallest bar Ø16)
  • PASSspan 1: stirrup spacing outside ℓo 08 §21.5.3.4
    s = 7 in ≤ d/2 = 10.9 in
  • PASSspan 1: laterally supported bars hx ≤ 14 in 08 §21.5.3.3
    hx = 8.2 in with 2 legs across b = 12.0 in (a closed hoop)
  • PASSspan 1 within ℓo: Av ≥ Av,min 08 §11.4.6.3
    Av/s = 0.0812 vs 0.0100 in²/in (0.974 vs 0.120 in²/ft)
  • PASSspan 1 outside ℓo: Av ≥ Av,min 08 §11.4.6.3
    Av/s = 0.0348 vs 0.0100 in²/in (0.417 vs 0.120 in²/ft)
  • PASSspan 2: hoop zone = 2h from each face 08 §21.5.3.1
    ℓo = 48.0 in (2h = 48.0 in)
  • PASSspan 2: first hoop ≤ 2 in from the face 08 §21.5.3.2
    first hoop at 2.0 in
  • PASSspan 2: hoop spacing within ℓo 08 §21.5.3.2
    s = 3 in ≤ 3.8 in (6db governs of d/4 = 5.4, 6db = 3.8, 6 in = 6.0; smallest bar Ø16)
  • PASSspan 2: stirrup spacing outside ℓo 08 §21.5.3.4
    s = 7 in ≤ d/2 = 10.9 in
  • PASSspan 2: laterally supported bars hx ≤ 14 in 08 §21.5.3.3
    hx = 8.2 in with 2 legs across b = 12.0 in (a closed hoop)
  • PASSspan 2 within ℓo: Av ≥ Av,min 08 §11.4.6.3
    Av/s = 0.0812 vs 0.0100 in²/in (0.974 vs 0.120 in²/ft)
  • PASSspan 2 outside ℓo: Av ≥ Av,min 08 §11.4.6.3
    Av/s = 0.0348 vs 0.0100 in²/in (0.417 vs 0.120 in²/ft)

4. Design shear

  • PASSspan 1: hoops carry Ve 08 §21.5.4.1
    Ve = 53.0 kip (M 321 + 186 kip·ft over ln 14.50 ft, + Vg 18.0 kip); with 2 legs s needed 4.5 in, given 3 in
  • PASSspan 1: Vs ≤ 8√f'c·bw·d 08 §11.4.7.9
    Vs = 70.6 kip vs 131.8 kip
  • N/Aspan 1: Vc taken as zero within ℓo 08 §21.5.4.2
    φVc used = 0.0 kip; axial not read (Ag·f'c/20 = 57.6 kip) — condition (b) unverified
  • PASSspan 2: hoops carry Ve 08 §21.5.4.1
    Ve = 50.6 kip (M 292 + 186 kip·ft over ln 14.67 ft, + Vg 18.0 kip); with 2 legs s needed 4.7 in, given 3 in
  • PASSspan 2: Vs ≤ 8√f'c·bw·d 08 §11.4.7.9
    Vs = 67.5 kip vs 131.8 kip
  • N/Aspan 2: Vc taken as zero within ℓo 08 §21.5.4.2
    φVc used = 0.0 kip; axial not read (Ag·f'c/20 = 57.6 kip) — condition (b) unverified

5. Development & splices

  • PASSextra bars reach their development length 08 §12.2 / §21.7.5
    tightest: 1-d20 at support3, 54.0 in ≥ ℓd 37.3 in
  • N/Alap splice locations 08 §21.5.2.3
    the detailer doesn't lay out splices — confirm on the drawing: lap splices need hoops at min(d/4, 4 in) over the lap and aren't permitted within a joint, within 2h of a joint face, or where flexural yielding is likely
  • PASScolumn depth ≥ 20db through the joint 08 §12.2 / §21.7.5
    c1 = 18.0 in at support 2 vs 20db = 15.7 in (largest bar 0.787 in)
  • PASShooked bars develop in the end columns 08 §21.7.5.1
    support 1: ℓdh = 11.5 in for Ø20 vs c1 − 2 in = 16.0 in

6. Torsion & serviceability

  • PASStorsion steel Al distributed to the faces 08 §11.6.3.7
    side bars 6-d10 = 0.730 in² vs (2/3)Al = 0.600 in² (max Al = 0.90 in²)
  • PASSspan 1: torsion hoops ≤ min(ph/8, 12 in) 08 §11.6.6.1
    widest s = 7 in ≤ 7.3 in (ph = 58.4 in)
  • PASSspan 2: torsion hoops ≤ min(ph/8, 12 in) 08 §11.6.6.1
    widest s = 7 in ≤ 7.3 in (ph = 58.4 in)
  • N/Askin reinforcement for h > 36 in 08 §10.6.7
    max h = 24.0 in — not required
  • PASSminimum depth for deflection (normalweight) 08 §9.5.2.1
    span 2 (one end continuous): h = 24.0 in vs L/18.5 = 10.5 in

N/A is never "fine": it is a check the tool has no input for, left for you to confirm, with the reason.

Design checks

CheckDemandCapacityDCRStatus
support 1, top: required / provided2.65 in²2.67 in²0.993✓ OK
support 1, bottom: required / provided1.00 in²1.46 in²0.685✓ OK
mid-span 1, top: required / provided0.87 in²0.93 in²0.929✓ OK
mid-span 1, bottom: required / provided1.40 in²1.46 in²0.958✓ OK
support 2, top: required / provided2.33 in²2.40 in²0.974✓ OK
support 2, bottom: required / provided0.98 in²1.46 in²0.673✓ OK
span 1: Vs ≤ 8√f'c·b·d70.6 kip131.8 kip0.536✓ OK

Calculation

  1. 1Effective depth
    d = h - c_c - d_{hoop} - d_b/2
    d = 24.0 - 1.50 - 0.394 - 0.787/2
    d21.71 in

    With the larger straight bar, Ø20.

  2. 2Steel needed at support 1ACI318 10.5.1
    A_{s,req} = \max\!\left(A_{s,ETABS} + \tfrac{2}{3}A_l,\ A_{s,min},\ A_{s,seismic}\right)
    \text{top } 2.65,\quad \text{bottom } 1.00
    A_{s,req}2.65 in²

    ETABS: top 2.05, bottom 0.40, Al 0.90 in².

  3. 3Steel needed at mid-span 1ACI318 10.5.1
    A_{s,req} = \max\!\left(A_{s,ETABS} + \tfrac{2}{3}A_l,\ A_{s,min},\ A_{s,seismic}\right)
    \text{top } 0.87,\quad \text{bottom } 1.40
    A_{s,req}1.40 in²

    ETABS: top 0.30, bottom 1.20, Al 0.30 in². Top set by As,min (§10.5.1).

  4. 4Steel needed at support 2ACI318 10.5.1
    A_{s,req} = \max\!\left(A_{s,ETABS} + \tfrac{2}{3}A_l,\ A_{s,min},\ A_{s,seismic}\right)
    \text{top } 2.33,\quad \text{bottom } 0.98
    A_{s,req}2.33 in²

    ETABS: top 1.80, bottom 0.45, Al 0.80 in².

  5. 5Continuous barsACI318 21.5.2.1
    A_s = \textstyle\sum n\,\pi d_b^2/4
    \text{top } 3-Ø16 = 0.93\ \text{in}^2,\quad \text{bottom } 3-Ø20 = 1.46\ \text{in}^2
    A_{s,top}0.93 in²

    Top: the least top requirement along the beam (and ¼ or ⅕ of the largest at a face); bottom: the largest mid-span requirement and As,min — both at least 2 bars.

  6. 6Extra top 1-Ø20 + 4-Ø16 at support 1 — cut-off from the moment diagramACI318 12.10.3
    L = \max\!\left(x_{\phi M_n = M_u} + \max(d, 12d_b),\ \ell_d\right)
    L = \max(86.2,\ 37.3) \to 87\ \text{in}
    L87 in

    Continuing bars 0.93 in² carry φMn 88.5 kip·ft; into span 1: φMn of the continuing bars met at 64.5 in from the face (Mpr + gravity); Vu 35.0 ≤ ⅔φVn 39.1 kip (§12.10.5). + max(d, 12db) = 21.7 in; ℓd 37.3 in (SMF §21.7.5 (3.25·ldh)). moment diagram + d or 12db (§12.10.3) governs: 7'-3" past the face.

  7. 7Extra top 1-Ø20 at support 2 — cut-off from the moment diagramACI318 12.10.3
    L = \max\!\left(x_{\phi M_n = M_u} + \max(d, 12d_b),\ \ell_d\right)
    L = \max(81.1,\ 37.3) \to 84\ \text{in}
    L84 in

    Continuing bars 0.93 in² carry φMn 88.5 kip·ft; into span 2: φMn of the continuing bars met at 59.4 in from the face (Mpr + gravity); Vu 33.4 ≤ ⅔φVn 39.1 kip (§12.10.5); back into span 1: φMn of the continuing bars met at 58.7 in from the face (Mpr + gravity); Vu 34.4 ≤ ⅔φVn 39.1 kip (§12.10.5). + max(d, 12db) = 21.7 in; ℓd 37.3 in (SMF §21.7.5 (3.25·ldh)). moment diagram + d or 12db (§12.10.3) governs: 7'-0" past the face.

  8. 8Extra top 2-Ø20 at support 2 — cut-off from the moment diagramACI318 12.10.3
    L = \max\!\left(x_{\phi M_n = M_u} + \max(d, 12d_b),\ \ell_d\right)
    L = \max(67.2,\ 37.3) \to 69\ \text{in}
    L69 in

    Continuing bars 1.42 in² carry φMn 132.2 kip·ft; into span 2: φMn of the continuing bars met at 45.5 in from the face (Mpr + gravity); Vu 36.5 ≤ ⅔φVn 39.1 kip (§12.10.5); back into span 1: φMn of the continuing bars met at 44.9 in from the face (Mpr + gravity); Vu 36.7 ≤ ⅔φVn 39.1 kip (§12.10.5). + max(d, 12db) = 21.7 in; ℓd 37.3 in (SMF §21.7.5 (3.25·ldh)). moment diagram + d or 12db (§12.10.3) governs: 5'-9" past the face.

  9. 9Probable-moment shear VeACI318 21.5.2.1
    V_e = \dfrac{M_{pr,top} + M_{pr,bot}}{\ell_n} + V_g
    V_e = \dfrac{321.2 + 186.0}{14.50} + 18.0
    V_e53.0 kip

    M from As 2.67 (top) and 1.46 in² (bottom) at 1.25·fy; Vg as read or typed.

  10. 10Hoop spacing from VeACI318 11.2.1 / Eq. 11-3
    s = \dfrac{A_v f_{yt} d}{V_e/\phi - \phi V_c}
    s = \dfrac{0.243 \cdot 60 \cdot 21.71}{70.6}
    s4.5 in

    φVc = 0 within ℓo (§21.5.4.2).

  11. 11Hoops within 2h of each faceACI318 21.5.2.1
    s \le \min(s_{code}, s_{demand}, s_{V_e}, s_{torsion})
    \text{Ø10, 2 legs @ 3 in, governed by \S 21.5.3}
    s3 in

    Zone 4'-0"; 2 legs: a closed hoop.

  12. 12Stirrups betweenACI318 21.5.2.1
    s \le \min(d/2, s_{demand}, s_{torsion})
    \text{Ø10, 2 legs @ 7 in, governed by torsion (\S 11.6.6.1)}
    s7 in

    Zone 8'-0"; 2 legs: a closed hoop.

  13. 13Hook of the continuous top bars at the end columnACI318 12.5
    \ell_{dh} = \dfrac{f_y d_b}{65\sqrt{f'_c}} \ge 8d_b,\ 6\text{ in}
    \ell_{dh}(\text{Ø16})
    \ell_{dh}9.2 in

Notes

  • Checklist: 39 pass, 0 fail, 6 for you to confirm (N/A). Sheet for span 1 of 2 (B5).

Assumptions

  • The steel each location needs is ETABS's concrete beam design (top and bottom As, Av/s, Al, At/s), the largest over the outer tenth of each span at a support and over the middle third at mid-span, plus (2/3)·Al on each of top and bottom as the owner's Beam_DCR workbook takes it.
  • SMF: As,min (§10.5.1) on both faces everywhere (§21.5.2.1); the moment ratios (§21.5.2.2: M+ ≥ ½ M− at a face, any section ≥ ¼ of the largest) through Mn, not the steel area.
  • Bars of the sizes ticked (Ø16, Ø20, Ø25, Ø28, Ø32), mirror-symmetric (two of one size, then a centre bar or a ring of another size), the narrowest web setting how many fit a layer — by CRSI's table of the most bars in a single layer (overall diameters, the corner bars in the hoop's bends, clear space ≥ 1 in, db and 4/3 × ¾ in aggregate), the size giving the fewest layers chosen first, extras filling the continuous bars' layer before the next; extra bars cut where the moment diagram lets them go, as PCA Notes' Example 29.2: past the point where φMn of the continuing bars meets Mu by max(d, 12db) (§12.10.3), at least ℓd past the face (§12.10.4), the farthest third of a support's top steel past the inflection point by d, 12db or ℓn/16 (§12.12.3), and §12.10.5 checked at the cut (Vu ≤ ⅔φVn, else on into compression); the diagram the envelope of ETABS's M3 (or the moment of the steel it asked for) and, in an SMF, the probable moments at the faces with the gravity load (w = 2Vg/ℓn, ¾ of it for the negative moments); rounded up to 3 in. The drawing measures them from the column faces.
  • Hoops Ø10, 2 legs or more, each zone as it needs: within 2h of an SMF's face every corner and alternate bar held, none more than 6 in clear from a held one (§21.5.3.3, §7.10.5.3); a crosstie added where ETABS's demand or Ve would close the hoops below 4 in (torsion on the two outer legs only). Spacing: within 2h of each face at the least of the code limit, ETABS's demand, the capacity-design shear and the torsion limit; between, d/2 or less.

What this calculator does not check

  • Lap splices are not laid out — the checklist names the rule to confirm on the drawing.
  • Rectangular webs only: a tee is detailed as its web.
  • The demand is ETABS's; a change to the model needs the design run and the beam read again.

Results are for preliminary sizing and educational use. They are not a design and must be reviewed, verified and sealed by a licensed or registered engineer before being used in construction.